A can do 50% of the job in 16 days, B can do 1/4th of the job in 24 days. In how many days can they do 3/4 th of the job working together?
My approach.
A can complete the job in 32 days alone
B can complete the job in 96 days alone.
Together they can complete the job in ?
A rate of building something is 3 times the rate of B assuming 96 houses need to be build.
A + B in 1 day is going to build - 4 houses.
total work assumed here is 96 so .
96/4 = 24days for total work. But, we need to 3/4 of the work only so the answer is 24 * 3 /4 = 18days.
$A$ takes $32$ days to do it fully. So, $A$ does $\frac{1}{32}$ of the work in a single day. Similarly, $B$ does $\frac{1}{96}$ of the work in a single day. Together they do $\frac{1}{32}+\frac{1}{96}=\frac{1}{24}$ of work in single day. So together they take $24$ days to do complete work and hence $18$ days to do $75\%$ of the work.