49 Painters are required to complete a painting job in 12 days . However, due to unforeseen circumstances , there was a delay and only one third of the job was completed in 5 days . Assuming that all Painters worked at the same initial rate , how Many more Painters are needed for the rest of the job to be completed as scheduled ?
I'm not quite sure on how to approach this qn ..
Without delay the question hints at this rate: $$ 49 \cdot r \cdot 12 = W = 1 \Rightarrow \\ r = 1/(49\cdot 12) $$ where $W$ is the amount of work to be done.
They are now left with $1-1/3$ of the work and $12-5$ days, this has to do be done with $49+k$ painters, which can do $$ (49 + k) r (12-5) = (1- 1/3) $$ So insert the rate $r$ and solve for the number of extra painters $k$.
Spoiler: