Allen can finish a job in $6$ days. If Andrea works with him as they finish the job in $2$ days, how many days will it take Hermione to finish the job alone?
I'm confused as how to build up an equation for this one. Is it built up like $\frac16+\frac12+\frac1x= 1$? Any kind of help will do.
(I am assuming you meant Andrea when you said “Hermione”, otherwise this question is unsolvable.)
“Allen can finish the job in $6$ days” is equivalent to “Allen does $\frac16$ of the job in one day”. Using the same logic we can say Andrea and Allen finish $\frac12$ of the job in one day.
The total contribution of Andrea is $\text{how much the 2 people contribute together - how much Allen contributes}=\frac12-\frac16$.
Once you find out how much Andrea contributes in a day, you can find out how long it takes her to finish the job by herself.